Most ACDB and DCDB problems on rooftop solar sites are not caused by bad components. They are caused by boxes that were never sized for the system they were installed on. A 32A MCB on a 10kW three-phase inverter, a 600V DC SPD on a string that reaches 640V on a cold morning, a DC isolator rated for AC duty. Each of these looks fine on the day of commissioning and fails months later.
This guide shows how to size an ACDB and DCDB correctly for systems from 1kW to 100kW. It is written by the engineering team at Synchro Electricals, a Rajkot-based manufacturer of solar ACDB DCDB boxes, and it uses the same method we follow when we design boxes for EPC contractors and rooftop installers across India.
The incomer is not the only consideration. Cable size, ambient temperature inside the box, and the number of inverters feeding one ACDB all change the final choice. A 100kW plant built from two 50kW inverters needs either two outgoing feeders in one ACDB or two separate ACDBs, which changes the busbar and enclosure size.
What ACDB and DCDB Actually Do
A solar plant has two electrical sides, and each needs its own protection box.- DCDB (DC Distribution Box): sits between the PV strings and the inverter. It isolates the strings, protects the DC cables and inverter from surges, and in larger systems protects strings from reverse current.
- ACDB (AC Distribution Box): sits between the inverter and the building’s main panel or net meter. It protects the inverter output cable, isolates the inverter for maintenance, and protects against surges coming from the grid side.
The Inputs You Need Before Sizing
Collect these values first. Without them, any sizing is a guess.| Input | Where to find it | Used for |
|---|---|---|
| Inverter maximum AC output current | Inverter datasheet | ACDB MCB/MCCB rating |
| Grid connection (single-phase 230V or three-phase 415V) | DISCOM sanction, site survey | ACDB pole count, SPD type |
| Number of MPPTs and strings per MPPT | Inverter datasheet, string layout | DCDB input/output count |
| Module Voc and Isc at STC | Module datasheet | DC voltage and current ratings |
| Voc temperature coefficient | Module datasheet | Cold-morning maximum string voltage |
| Lowest site temperature | Local weather data | Maximum string voltage |
| Inverter maximum DC input voltage | Inverter datasheet | DC component voltage class |
| Fault level at the connection point | DISCOM or site data | Breaking capacity of AC devices |
How to Size the ACDB
Step 1: Find the design current
Use the inverter’s maximum AC output current from the datasheet. If you only have the kW rating, calculate it:- Single-phase: current = power ÷ 230V
- Three-phase: current = power ÷ (1.732 × 415V)
Step 2: Apply a continuous-load margin
Solar inverters run at or near full output for hours every day. Breakers are not meant to sit at 100% of their rating for long periods. Multiply the design current by 1.25, then choose the next standard MCB or MCCB rating.Step 3: Choose the device type
- Up to about 63A: MCB, with breaking capacity matched to the site fault level (commonly 10kA for most rooftop sites).
- Above 63A: MCCB, with adjustable thermal settings where the current is close to a step.
- Add an RCCB or RCBO where the DISCOM, the inverter manufacturer or the building wiring rules require it. Check which RCD type the inverter manufacturer recommends.
Step 4: Add AC surge protection
An AC SPD (usually Type 2) protects the inverter from grid-side surges. Its continuous operating voltage must suit the grid. Single-phase boxes use a 1P+N arrangement, three-phase boxes use 3P+N.ACDB sizing table (indicative)
Currents below are calculated at unity power factor. Always confirm against the inverter’s maximum output current.| System size | Grid | Approx. output current | Current × 1.25 | Suggested incomer |
|---|---|---|---|---|
| 1 kW | 1-phase 230V | 4.3 A | 5.4 A | 10 A MCB, 2P |
| 2 kW | 1-phase 230V | 8.7 A | 10.9 A | 16 A MCB, 2P |
| 3 kW | 1-phase 230V | 13.0 A | 16.3 A | 20 A MCB, 2P |
| 5 kW | 1-phase 230V | 21.7 A | 27.2 A | 32 A MCB, 2P |
| 5 kW | 3-phase 415V | 7.0 A | 8.7 A | 10–16 A MCB, 4P |
| 10 kW | 3-phase 415V | 13.9 A | 17.4 A | 20 A MCB, 4P |
| 15 kW | 3-phase 415V | 20.9 A | 26.1 A | 32 A MCB, 4P |
| 20 kW | 3-phase 415V | 27.8 A | 34.8 A | 40 A MCB, 4P |
| 25 kW | 3-phase 415V | 34.8 A | 43.5 A | 50 A MCB, 4P |
| 30 kW | 3-phase 415V | 41.7 A | 52.2 A | 63 A MCB, 4P |
| 50 kW | 3-phase 415V | 69.6 A | 87.0 A | 100 A MCCB, 4P |
| 75 kW | 3-phase 415V | 104.3 A | 130.4 A | 160 A MCCB, 4P |
| 100 kW | 3-phase 415V | 139.1 A | 173.9 A | 200 A MCCB, 4P |
How to Size the DCDB
Step 1: Calculate the maximum string voltage
Module voltage rises as temperature falls. The highest string voltage occurs on a cold, bright morning, not at noon. Use the module’s Voc temperature coefficient: Max string Voc = modules in series × module Voc (STC) × [1 + |coefficient| × (25 − lowest site temperature)] Example: 10 modules with a Voc of 49.5V give 495V at STC. With a coefficient of −0.27%/°C and a lowest temperature of 10°C, the maximum is about 515V. A 600V DCDB works here. A string of 12 such modules would reach about 618V, so it needs 1000V-class components.Step 2: Choose the voltage class
Match every DC component (isolator, MCB or fuse, SPD) to the voltage class at or above the maximum string voltage and the inverter’s maximum DC input.| Voltage class | Typical use |
|---|---|
| 600V DC | Small single-phase rooftop systems with short strings |
| 1000V / 1100V DC | Most three-phase rooftop and C&I systems |
| 1500V DC | Utility-scale plants; see our 1500VDC Solar DCDB Panel |
Step 3: Size the current rating
DC devices are sized on the module’s short-circuit current (Isc), with a margin. A common design rule is at least 1.25 × Isc for switches and cables. Where string fuses are used, IEC 62548 places the fuse rating between 1.5 × Isc and 2.4 × Isc, and not above the module’s maximum series fuse rating.Step 4: Decide whether string fuses are needed
With one or two strings in parallel per input, a faulty string cannot receive enough reverse current to damage itself, so fuses are usually not required. With three or more strings in parallel, the healthy strings can push current into a faulted one. That is when gPV fuses become necessary.Step 5: Add DC surge protection
Choose a PV-rated DC SPD whose continuous operating voltage (Ucpv) is at or above the maximum string voltage. Most rooftop systems use Type 2. Read our guide on Type 1 vs Type 2 SPD in solar DCDB (activate once live) for when Type 1 is needed.DCDB configuration table (indicative)
| System size | Typical inverter | DCDB configuration | Voltage class | Fuses? |
|---|---|---|---|---|
| 1–3 kW | 1-phase, 1 MPPT | 1 in 1 out | 600V | No |
| 3–5 kW | 1-phase, 1–2 MPPT | 1 in 1 out or 2 in 2 out | 600V or 1000V | No |
| 5–10 kW | 3-phase, 2 MPPT | 2 in 2 out | 1000V / 1100V | No |
| 10–25 kW | 3-phase, 2–3 MPPT | 2–4 inputs | 1000V / 1100V | Only if 3+ strings in parallel |
| 25–50 kW | 3-phase, 3–6 MPPT | 4–8 inputs, or per-MPPT isolation | 1000V / 1100V | Depends on string layout |
| 50–100 kW | One or more string inverters | Multi-input DCDB or string combiner box | 1000V / 1100V | Usually yes when strings are paralleled |
Common Sizing Mistakes We See
| Mistake | What happens | How to avoid it |
|---|---|---|
| Sizing the AC MCB on nominal kW instead of maximum output current | Nuisance tripping on hot afternoons | Use the datasheet maximum current × 1.25 |
| Using an AC isolator or AC MCB on the DC side | DC arcs do not self-extinguish; the device can burn | Use devices rated for DC-PV duty at the system voltage |
| Ignoring cold-morning Voc | SPD or isolator works above its rating | Calculate Voc at the lowest site temperature |
| Oversized string fuses | Fuse does not clear a reverse-current fault | Stay within 1.5–2.4 × Isc and the module’s fuse limit |
| Mixed polarity labelling on bulk orders | Wrong termination on site | Insist on standard terminal marking across every unit |
| Box too small for heat | Breakers derate and trip | Size the enclosure for heat, not just component count |
Sizing for Bulk Rollouts
If you are buying ACDB and DCDB boxes for 30, 100 or 500 rooftop installations, sizing becomes a standardisation exercise. Group your projects into a small number of system-size bands (for example 3kW, 5kW and 10kW), fix the bill of materials for each band, and get each design approved once. Every unit in that band is then built to the same drawing, wiring colour code and terminal marking. This cuts site errors and makes spares simple. It also makes inspection faster, because your QA team checks every box against one approved design. Read more about this in our guide on how solar EPCs can source ACDB and DCDB in bulk (activate once live).Why Work With Synchro Electricals
Synchro Electricals has manufactured electrical panels in Rajkot, Gujarat since 2018 and is ISO 9001:2015 certified. For ACDB DCDB boxes, we:- design each box from your inverter and module datasheets, not from a generic kW chart
- submit drawings for your approval before components are ordered
- build both single-phase and three-phase configurations, from 1-in-1-out to multi-input DCDBs
- carry out insulation resistance, high-voltage and functional tests, and supply a test report with every order
- support bulk orders where every unit is built to one approved design