A panel arrives on site, and the commissioning engineer asks for the wiring diagram. Nobody can find the latest revision. The protection settings sheet was never sent. The O&M team, two years later, cannot identify a replacement SPD because the BOM listed “SPD, 1000V” with no make or model.
These are documentation failures, not panel failures, but they cost just as much time. For EPC projects, the documentation pack is also what consultants approve, what inspectors check and what decides whether a supplier is tender-ready. This guide lists every document a buyer should expect, when it should arrive and what it should contain. It is written by the engineering team at Synchro Electricals.
The Documentation Pack at a Glance
| Stage | Document | Purpose | Main user |
|---|---|---|---|
| Offer | Technical offer and datasheet | Shows what is being quoted | Procurement, consultant |
| Offer | Compliance and deviation statement | Lists where the offer differs from the specification | Consultant |
| Approval | GA (general arrangement) drawing | Dimensions, layout, cable entry, mounting | Civil, electrical and site teams |
| Approval | SLD (single-line diagram) | Electrical scheme and ratings | Consultant, design engineer |
| Approval | Schematic and wiring diagrams | Control and power wiring, terminal numbers | Commissioning, O&M |
| Approval | BOM (bill of materials) | Make, model and rating of every component | QA, O&M, spares |
| Approval | Busbar and heat calculations (where required) | Proves busbar and enclosure sizing | Consultant |
| Approval | Nameplate and label details | Ratings and identification | QA, inspectors |
| Manufacturing | Quality plan / ITP | Inspections and tests with acceptance criteria | QA |
| Pre-dispatch | Routine test reports | Results for each panel | QA, inspectors |
| Pre-dispatch | FAT report and punch list | Witnessed results and closure | Buyer, consultant |
| Pre-dispatch | Calibration certificates | Validity of test instruments | QA |
| Pre-dispatch | Design verification documents | IEC 61439 evidence for the panel type | Consultant |
| Dispatch | Packing list and marking | Identifies each package | Logistics, site stores |
| Handover | As-built drawings | Final, correct drawings | O&M |
| Handover | Installation, operation and maintenance manual | Safe installation and upkeep | Site and O&M teams |
| Handover | Component datasheets and certificates | Reference and warranty | O&M |
| Handover | Recommended spares list | Planning stock | O&M |
| Handover | Warranty certificate | Terms and contacts | Owner |
What Good Documents Look Like
GA drawing
It shows outer dimensions, weight, front and side views, door swing, cable entry positions and gland sizes, mounting or foundation details, lifting points and the location of the nameplate. For outdoor solar boxes, it should also show the mounting method on the structure.
Single-line diagram
It shows every incomer and outgoing, device type and rating, busbar rating, CT and PT ratios, SPD locations and the earthing arrangement. For an 800Vac panel, it should state the rated operational voltage and the short-circuit rating.
Wiring diagrams
They show every wire with its number, colour and size, and every terminal with its number. Good wiring diagrams make commissioning and fault-finding fast. Our post on panel wiring design best practices covers what good wiring looks like in the panel itself.
BOM
A good BOM names the make, model, rating and quantity of every component, including SPDs, fuses, isolators, glands and terminals. “Equivalent” or “reputed make” entries make the BOM useless for O&M and spares.
Test reports
Each report should identify the panel (serial number), the test performed, the instrument used, the result and the acceptance criterion, signed and dated. For bulk solar boxes, it should be traceable to each unit or batch.
Solar-Specific Documents
| Product | Extra documents to ask for |
|---|---|
| Solar ACDB/DCDB boxes | Design band sheet showing which box suits which system size; polarity and labelling scheme |
| String combiner boxes | String input numbering scheme; fuse rating table; SPD Ucpv and Type statement |
| String monitoring boxes | Modbus register map; addressing scheme; communication wiring diagram |
| 800Vac panels | Protection settings sheet; IEC 61439 design verification evidence; auxiliary supply scheme; SCADA signal list |
Revision Control
Most documentation problems come from revisions, not missing documents. Ask for:
- a document register listing every document, its number and current revision
- a revision block on every drawing with date, description and approver
- clouded changes on revised drawings
- final as-built drawings issued only after FAT and any site changes
- both PDF and editable CAD (DWG) formats, where the contract allows
Why Documentation Decides Tender Readiness
International and utility EPC tenders often reject suppliers who cannot produce complete submittals. Consultants approve equipment based on drawings, BOMs and compliance statements, long before they see the panel. A manufacturer who produces a complete, consistent pack the first time shortens the approval cycle and reduces risk for the EPC. See electrical panel manufacturing for international EPC specifications.
Why Work With Synchro Electricals
At Synchro Electricals, drawings are submitted for your approval before we order components, and every order ships with a test report. We work under an ISO 9001:2015 certified quality system (certificates), welcome witnessed FATs at our Rajkot factory, and provide after-sales technical support. For the testing side of documentation, see our solar panel FAT checklist (activate once live) and the IEC 61439 verification guide.
Conclusion
A complete documentation pack covers the panel’s whole life: offer, approval, manufacturing, testing, dispatch and handover. Ask for it in the RFQ, check it at each stage, and insist on a named BOM and revision control. The panel will be easier to approve, commission and maintain, and your project file will stand up to any audit.
Ask our team for a sample documentation pack for your panel type.
FAQs
1. What documents come with an electrical panel?
Typically GA drawings, SLD, wiring diagrams, BOM, test reports, FAT report, as-built drawings, an O&M manual, component certificates and a warranty certificate.
2. What is a GA drawing?
A general arrangement drawing showing the panel’s dimensions, layout, cable entries, mounting and lifting details.
3. What is the difference between an SLD and a wiring diagram?
An SLD shows the electrical scheme in single-line form with ratings. A wiring diagram shows every wire and terminal for building and commissioning the panel.
4. Why should a BOM name component makes?
Without makes and models, the buyer cannot verify quality, order matching spares or claim component warranties.
5. What should a panel test report include?
The panel serial number, tests performed, instruments used, results, acceptance criteria, date and signature.
6. What are as-built drawings?
Final drawings that reflect the panel exactly as built, including any changes made during manufacturing, FAT or site work.
7. What is a compliance and deviation statement?
A document listing each specification clause and whether the offer complies, with any deviations explained.
8. What documents are needed for consultant approval?
Usually the GA, SLD, wiring diagrams, BOM, datasheets, certificates and a compliance statement.
9. What is a Modbus register map?
A table listing each data point a monitoring device sends, with its address and format, used to integrate it into SCADA.
10. Do solar combiner boxes need a documentation pack?
Yes. A GA, wiring diagram, BOM with fuse and SPD details, test reports and a string numbering scheme are standard.
11. Should I get drawings in DWG format?
Where the contract allows, editable CAD files help the EPC integrate panel drawings into the project’s own drawings.
12. What is a protection settings sheet?
A document listing the trip settings for each breaker or relay, used during commissioning and maintenance.
13. When should documents be submitted for approval?
Before components are ordered, so any changes can be made without rework.
14. What is a document register?
A list of every project document with its number, title and current revision.
15. Does Synchro Electricals provide full documentation?
Yes. We submit drawings for approval before production and supply test reports with every order. Contact us for your project’s documentation requirements.