panel FAT checklist

Factory Acceptance Test (FAT) for Solar Panels: What Buyers Should Witness

A factory acceptance test (FAT) is the last point at which a panel problem is cheap to fix. Once boxes are on a truck, every defect costs a site visit, a delay or a return shipment. For solar projects, where hundreds of combiner boxes or DCDBs may be built to one design, a defect found at FAT can be corrected across the whole batch. Found on site, it may already be on every roof.

This guide sets out what buyers should witness during a FAT for solar electrical panels: ACDB/DCDB boxes, string combiner and monitoring boxes, and 800Vac panels. For the general difference between factory and site testing, see our post on electrical panel FAT vs SAT.

Before the FAT: Prepare Properly

Preparation item Why it matters
Approved drawings and BOM The FAT checks the panel against these, nothing else
Inspection and test plan (ITP) Lists every test, method, acceptance criterion and who witnesses
Sampling plan (for bulk boxes) Agreed number of units to inspect and test in each batch
FAT notice Enough notice for your inspector to attend
Test instrument calibration certificates Proves the test results are valid
Component certificates SPD, isolator, fuse and breaker certificates ready for review
Punch list format How defects will be recorded and closed

What to Witness: ACDB/DCDB Boxes

For bulk rooftop orders, inspect a sample from each design band and each batch.

  • Enclosure type, size, IP rating label and UV-stabilised material match the BOM
  • Every component’s make, model and rating match the approved BOM
  • DC isolator rated for DC-PV duty at the system voltage
  • DC MCB polarity correct; fuse class gPV where fitted
  • SPD Ucpv, Type and status indicator correct
  • Wiring colours, ferrules and terminal tightness (torque marks where used)
  • Glands, blanking plugs and gaskets fitted
  • Labels: warning, polarity, rating, band and serial number
  • Insulation resistance test witnessed and recorded
  • Dielectric (high-voltage) test witnessed on sample units
  • Functional check: switching of MCB/isolator, RCCB test button where fitted

What to Witness: String Combiner and Monitoring Boxes

  • Number of inputs and outputs matches the drawing
  • Fuse rating and class (gPV, correct voltage) in every holder
  • Fuse holders and isolator rated for the system voltage (for example 1500V DC)
  • Busbar size, plating and insulation
  • Polarity and continuity from every input to the output
  • Insulation resistance between poles and to earth, recorded per unit
  • Dielectric test on sample units, at the voltage in the ITP
  • SPD rating, earthing lead length and status contact
  • For monitoring boxes: current sensor readings checked by injecting a test current; communication tested on RS485 Modbus with addressing as specified
  • Enclosure sealing, breather and mounting arrangement

Related reading: 1500V string combiner box specification checklist.

What to Witness: 800Vac Panels

An 800Vac panel is a heavier piece of equipment, and its FAT is closer to that of a PCC panel.

  • General arrangement, dimensions, cable entry and lifting arrangement
  • Device ratings: every main-circuit device rated for 800V AC
  • Busbar size, supports, clearances and segregation as per the drawing
  • Torque marking on busbar joints and power terminals
  • Earth bus continuity and door earthing
  • Insulation resistance and power-frequency dielectric test
  • Breaker operation, interlocks and trip tests (secondary injection where specified)
  • Protection relay or release settings as per the approved settings sheet
  • Metering: CT polarity and meter readings checked by injection
  • Auxiliary supply, panel heaters, lighting and fans
  • Communication to SCADA (Modbus RS485 or Ethernet) checked
  • Design verification documents (IEC 61439) available for review

For what design verification means for these panels, see type-tested 800Vac panels and IEC 61439 and our IEC 61439 verification guide.

Documents to Review at FAT

  • Routine test reports for every unit (or every unit in the batch)
  • Calibration certificates of test instruments
  • Component certificates and datasheets
  • Design verification documents for the panel type
  • As-built drawings, if any change was made after approval
  • Packing and marking plan

Common FAT Findings on Solar Panels

Finding Typical correction
Component make changed from the approved BOM Replace, or obtain formal approval for the substitute
Polarity-sensitive DC MCB wired backwards Rewire and recheck the whole batch
Fuse rating different from the drawing Replace and check stock control
Missing blanking plugs or loose glands Fit and recheck IP integrity
Labels missing or inconsistent Relabel the batch
Monitoring box address duplicated Re-address and retest communication
Loose busbar joint (torque mark missing) Re-torque and mark all joints

After the FAT

  1. Sign the FAT report with all results and the punch list.
  2. The manufacturer closes each punch item with evidence (photos, retest results).
  3. Issue a dispatch clearance once open items are closed.
  4. Carry the FAT records into the site acceptance test (SAT) so the site team knows what was already verified.

Why Work With Synchro Electricals

Synchro Electricals welcomes witnessed FATs at our factory in Rajkot, Gujarat. We work to approved drawings and BOMs, carry out insulation resistance, high-voltage and functional tests, and supply a test report with every order. Our quality system is ISO 9001:2015 certified (certificates). We manufacture solar ACDB DCDB boxes, string combiner boxes, string monitoring boxes and the 800VAC Solar Type Tested Panel.

Conclusion

A good solar panel FAT is planned, not improvised. Agree on the ITP and sampling plan, check every component against the approved BOM, witness insulation and dielectric tests, test monitoring and protection functions, and close the punch list before dispatch. For bulk solar orders, a single FAT finding can protect hundreds of installations.

Plan a FAT with our team for your next solar order.

FAQs

1. What is a factory acceptance test for electrical panels?

A FAT is an inspection and set of tests carried out at the manufacturer’s factory, often witnessed by the buyer, to confirm the panel matches the approved design before dispatch.

2. What tests are done during a solar panel FAT?

Visual and BOM checks, insulation resistance, dielectric tests, polarity and continuity, functional tests, and communication tests for monitoring boxes.

3. How many units should be tested in a bulk FAT?

The number is agreed in the sampling plan of the ITP. Routine tests should still be done by the manufacturer on every unit.

4. What is an ITP?

An inspection and test plan. It lists each inspection and test, its method, acceptance criteria and who witnesses it.

5. What is the difference between FAT and SAT?

FAT is done at the factory before dispatch. SAT is done on site after installation, checking the panel in its real connections.

6. What should I check in a combiner box at FAT?

Input count, fuse rating and class, voltage ratings, polarity, insulation resistance, SPD details, enclosure sealing and monitoring functions.

7. How are string monitoring boxes tested at FAT?

By injecting test current into the sensors, checking the readings, and testing RS485 Modbus communication with the specified addressing.

8. What is tested on an 800Vac panel at FAT?

Device ratings, busbar and clearances, torque, insulation and dielectric tests, breaker and interlock operation, protection settings, metering and communication.

9. Should I check calibration certificates at FAT?

Yes. Test results are only valid if the instruments used are calibrated.

10. What happens if a defect is found at FAT?

It goes on the punch list. The manufacturer corrects it and provides evidence before dispatch clearance.

11. Can FAT be done remotely?

Some buyers accept video-witnessed FATs with test reports and photos. A physical visit gives more confidence for large orders.

12. Is a FAT needed for small rooftop orders?

For small orders, reviewing test reports and photos may be enough. For bulk orders, a sample FAT is strongly recommended.

13. What documents should I get after a FAT?

The signed FAT report, routine test reports, closed punch list and dispatch clearance.

14. Does a FAT replace type testing?

No. FAT checks individual panels against the approved design. Type testing or design verification proves the design itself.

15. Can I witness a FAT at Synchro Electricals?

Yes. Our factory in Rajkot welcomes witnessed FATs. Contact us to plan one.